Planned Highways Maintenance Works

Headley Road/Grayshott Road, Headley Down from Beech Hill Roundabout to Waggoners Way.
Mill Lane, Bordon from Liphook Road to High Street.
Standford Lane, Bordon from Mill Lane to Whitehill Road.

As part of Hampshire County Council’s annual Planned Maintenance programme, this email is to inform you that we will be undertaking carriageway surface dressing along the following.

Headley Road/Grayshott Road, Headley Down from Beech Hill Roundabout to Waggoners Way.
Mill Lane, Bordon from Liphook Road to High Street.
Standford Lane, Bordon from Mill Lane to Whitehill Road.

These works are currently programmed to start on Monday 19th May 2025 and are expected to take up to 5 days to complete. During this time the road will be closed from approximately 0930 – 1900 avoiding peak hours but will be open outside of these hours. Vehicular access for residents and businesses will not be possible during the works. Pedestrian access to properties will not be affected, and emergency vehicles will have access at all times.

Whilst there is an allowance within the time periods shown above for delays, there may be times when we have to postpone works at very short notice; based on the latest weather forecasts, this can occur just prior to works commencing.

We will always look to provide up to date information wherever we can, but sometimes these last-minute decisions can be difficult to relay to the travelling public in a timely manner. When we can, any significant changes to the scheduled dates will be made clear on the yellow sign boards located at the works limits. Information signs advising road users will be erected before the start of works. The attached letter will be sent to local residents and businesses, East Hants District Council and relevant Parish Councils have been copied into this email to advise them accordingly.