News Update on the Headley Pavilion September 2025

The rate of progress is impressive. When we attend the monthly site meetings it seems like we are entering a different building! All the ground work (drains etc.) is complete, the new flat roof and balcony is complete, the roof repairs have been done and tiling was completed at the end of August. Electrical installation is well under way including a new security system and an induction loop for people with hearing aids is under the main hall floor.

As soon as the new screed in the main hall floor has hardened, work can continue in that area. In the meantime, fitting out of corridors, changing rooms and toilets is continuing. This includes electrics, plumbing, heating and ventilation so there is still plenty to be done.

We have now approved the bar and kitchen fittings. These will be built to last and continue to look good for years to come. We can’t want for the Grand Opening so everyone can see the finished building! However, we will have to be patient and bring you news as the work progresses month by month.

Similar Posts

  • News Update Headley Pavilion Project March 2026

    As anyone who has had any major work done on their house will know, there isn’t an exact moment when it is “finished”! The Flint Construction team worked extremely hard to get everything ready for the scheduled handover in February, and all of their work inside the building was completed. Unfortunately, due to the weather,…

  • Please can we book the Pavilion???

    I’m sure you have been following the build progress for our exciting project to upgrade the pavilion building on Mill Lane Playing Fields. There will be a larger hall, a fully fitted bar and a commercial specification kitchen. Upstairs the two smaller rooms will be redecorated and the balcony has been significantly extended over the…

  • News Update on the Headley Pavilion Project January 2026

    A highlight of December was hosting a visit from over 50 pupils from The Holme School, Headley. Site Manager Neil Kelly with his team and Gordon Kerr the architect had prepared a guided tour to show the children what goes on behind the safety fence around a busy building site. They also explained how the…

  • News Update Headley Pavilion July 2025

    Every month, two Headley Parish Councillors attend a full Site Meeting at the Headley Pavilion with the architect, Flint Construction, the sub-contractors and consultants. This ensures that there is full and open discussion between HPC as the client, the suppliers and professional advisors. This also means that queries can be resolved quickly and decisions taken…

  • News Update on the Headley Pavilion October 2025

    Heading photo: new hall floor; door and window frames under construction. A lot of building work happens before you can see progress. For the last few months the site has been a flurry of activity but most of the work will end up hidden from view. This month is different, because suddenly we can really…

  • Headley Pavilion Project – News Update April 2025

    The past month has been full of activity! After issuing an Invitation to Tender in 2024, the responses were carefully analysed in December and January which resulted in the selection of the most suitable contractor. After finalising contractual and financial details we signed contracts with Flint Construction Ltd., an Alresford-based company with considerable experience of…