News Update Headley Pavilion August 2025

The Flint Construction team have been making great progress and the overall shape of the new building is clearly visible. The heading photo shows the new entrance foyer leading into the extended hall space.

We previously had concerns about the condition of the hall floor under the vinyl covering, and when this was lifted it was confirmed that the concrete below was in poor condition. Having looked at a number of repair options none of which were guaranteed, we decided to dig up the entire floor and re-screed it. Although this is an additional expense, it has the advantage that we can bury heating pipes under the floor instead of running them along the walls, and we can install an induction loop for the audio system.

We have also been reviewing colour schemes for the public areas including options for a more dramatic wall treatment in the entrance foyer. We want it to be exciting, welcoming and inclusive so the choices here are very important even though it’s only paint!

When you are involved in a project of this scale, you realise just how many decisions have to be made even after the design is finalised. Our days are never without exchanges of emails between the builders, consultants, architect and Headley Parish Council about colours of railings, type of radiator, location of pipes and much, much more. It really is a team effort from all involved.

Despite the additional work on the hall floor, the project remains on budget and progressing according to expected timescales.

Neville Merritt
August 2025

Similar Posts

  • News Update on the Headley Pavilion November 2025

    Heading photo: the all-new foyer and hall extension with balcony above. The cooler months are now upon us, and that is good timing for the construction team because most of the external building work has been completed. Most of the scaffolding has been removed, leaving only a small section to enable them to lift the…

  • News Update Headley Pavilion Project March 2026

    As anyone who has had any major work done on their house will know, there isn’t an exact moment when it is “finished”! The Flint Construction team worked extremely hard to get everything ready for the scheduled handover in February, and all of their work inside the building was completed. Unfortunately, due to the weather,…

  • Headley Pavilion Project – News Update April 2025

    The past month has been full of activity! After issuing an Invitation to Tender in 2024, the responses were carefully analysed in December and January which resulted in the selection of the most suitable contractor. After finalising contractual and financial details we signed contracts with Flint Construction Ltd., an Alresford-based company with considerable experience of…

  • News Update Headley Pavilion June 2025

    The team from Flint Construction have been very busy in the last month and we are now seeing things appearing that weren’t there before! The rearrangement and additions of changing rooms, storage and toilets has needed new internal walls, so the bricklayers have been making new block walls and sealing up windows and door spaces…

  • News Update on the Headley Pavilion Project January 2026

    A highlight of December was hosting a visit from over 50 pupils from The Holme School, Headley. Site Manager Neil Kelly with his team and Gordon Kerr the architect had prepared a guided tour to show the children what goes on behind the safety fence around a busy building site. They also explained how the…

  • PEG Working Party at Standford Green

    This week Cllr. Steve Thair organised a working party of Headley’s Parish Enhancement Group members to clear the pathway that runs from Standford Green to the Hatch Farm Watermeadows. This is a permissive path and the surrounding vegetation had become very overgrown along its length. With the kind permission of the landowner, Cllr. Steve Thair,…