HPC News

  • News Update on the Headley Pavilion November 2025

    Heading photo: the all-new foyer and hall extension with balcony above. The cooler months are now upon us, and that is good timing for the construction team because most of the external building work has been completed. Most of the scaffolding has been removed, leaving only a small section to enable them to lift the…

  • News Update on the Headley Pavilion October 2025

    Heading photo: new hall floor; door and window frames under construction. A lot of building work happens before you can see progress. For the last few months the site has been a flurry of activity but most of the work will end up hidden from view. This month is different, because suddenly we can really…

  • Please can we book the Pavilion???

    I’m sure you have been following the build progress for our exciting project to upgrade the pavilion building on Mill Lane Playing Fields. There will be a larger hall, a fully fitted bar and a commercial specification kitchen. Upstairs the two smaller rooms will be redecorated and the balcony has been significantly extended over the…

  • News Update on the Headley Pavilion September 2025

    The rate of progress is impressive. When we attend the monthly site meetings it seems like we are entering a different building! All the ground work (drains etc.) is complete, the new flat roof and balcony is complete, the roof repairs have been done and tiling was completed at the end of August. Electrical installation…

  • News Update Headley Pavilion August 2025

    The Flint Construction team have been making great progress and the overall shape of the new building is clearly visible. The heading photo shows the new entrance foyer leading into the extended hall space. We previously had concerns about the condition of the hall floor under the vinyl covering, and when this was lifted it…

  • News Update Headley Pavilion July 2025

    Every month, two Headley Parish Councillors attend a full Site Meeting at the Headley Pavilion with the architect, Flint Construction, the sub-contractors and consultants. This ensures that there is full and open discussion between HPC as the client, the suppliers and professional advisors. This also means that queries can be resolved quickly and decisions taken…

  • News Update Headley Pavilion June 2025

    The team from Flint Construction have been very busy in the last month and we are now seeing things appearing that weren’t there before! The rearrangement and additions of changing rooms, storage and toilets has needed new internal walls, so the bricklayers have been making new block walls and sealing up windows and door spaces…

  • Do you have ideas for Community Use of the Headley Pavilion?

    When the upgraded Headley Pavilion is reopened early in 2026, it will have some wonderful new facilities for both sporting and non-sports use. This includes an extended hall, new kitchen, bar, outdoor areas and of course improved changing rooms and toilets in addition to the upstairs rooms which will be available for booking. Opportunities include…

  • Headley Pavilion Project – News Update May 2025

    They say things have to get worse before they get better and that’s very true of any rebuild project! First of all, the premises have to be emptied, then all the areas of the building inside and outside have to be stripped out or demolished. Flint Construction have been busy doing just that, so although…

  • Headley Pavilion Project – News Update April 2025

    The past month has been full of activity! After issuing an Invitation to Tender in 2024, the responses were carefully analysed in December and January which resulted in the selection of the most suitable contractor. After finalising contractual and financial details we signed contracts with Flint Construction Ltd., an Alresford-based company with considerable experience of…