Headley Pavilion Project – News Update May 2025

They say things have to get worse before they get better and that’s very true of any rebuild project! First of all, the premises have to be emptied, then all the areas of the building inside and outside have to be stripped out or demolished. Flint Construction have been busy doing just that, so although a lot of work has been done, not much can be seen from the outside.

What we can see however is the start of the work to create the new foyer, extended hall and larger balcony above. The old balcony has been dismantled, and the foundations have been created for the new walls around the foyer and main hall extension.

In our next news update we hope to bring you pictures from inside, but in the meantime, here is a photo of the external works in progress.

Similar Posts

  • News Update on the Headley Pavilion Project January 2026

    A highlight of December was hosting a visit from over 50 pupils from The Holme School, Headley. Site Manager Neil Kelly with his team and Gordon Kerr the architect had prepared a guided tour to show the children what goes on behind the safety fence around a busy building site. They also explained how the…

  • Introducing…The Parish Enhancement Group!

    The role of Headley Parish Council is very broad, so it makes sense to divide the activities up into dedicated Working Groups. These are not formal committees: the emphasis is on getting things done, not endless meetings! The Parish Enhancement Group (PEG) consists of five councillors and soon we hope, members of the local community…

  • News Update on the Headley Pavilion October 2025

    Heading photo: new hall floor; door and window frames under construction. A lot of building work happens before you can see progress. For the last few months the site has been a flurry of activity but most of the work will end up hidden from view. This month is different, because suddenly we can really…

  • Bus Shelters – Updated!

    It’s hard to get excited by bus shelters, but when you see the improvements it’s hard not to! Following on from our previous News item, the work funded by a grant from EHDC to clean and refurbish the bus shelters in Headley has been completed. The wooden bus shelter at Glebe Road has had a…

  • Do you have ideas for Community Use of the Headley Pavilion?

    When the upgraded Headley Pavilion is reopened early in 2026, it will have some wonderful new facilities for both sporting and non-sports use. This includes an extended hall, new kitchen, bar, outdoor areas and of course improved changing rooms and toilets in addition to the upstairs rooms which will be available for booking. Opportunities include…

  • You can save a tree!

    We are incredibly lucky to live in an area with so many trees for us enjoy and for the benefit of the natural environment. With increasing pressure from housing development, we must do all we can to protect what we have. Fortunately there is legislation for exactly that – the Tree Preservation Order (TPO). If…